Cases of oversized cargo transportation from China to Russia
  • Transporting a power transformer complex from Shenzhen to Sochi
    Task: deliver a heavy-duty transformer (total weight: 160 tons) for a substation modernization in Sochi within 30 days.
    Solution: 5 telescopic trailers with maximum width dimensions of 3.5 meters and height of 4 meters.
    Road transport from Shenzhen to Manzhouli (8 days);
    Consolidation at our temporary storage warehouse (3 days);
    Road transport from Manzhouli to Sochi (16 days);
    Oversized cargo transportation permits within the Russian Federation;
    Result: The transformer was delivered in 27 days, and the client was satisfied. The client confirmed the cargo's compliance with technical requirements and provided a full set of accompanying documents.
  • Transporting a disassembled industrial machine from Qingdao to Yekaterinburg
    Task: deliver a large metal-cutting machine (dimensions: 18 × 2.5 × 3 m, weight: 28 tons) from a plant in Qingdao to a machine-building plant in Yekaterinburg.
    Solution: Multimodal transportation: sea delivery of an open-top container from Qingdao to Vladivostok (14 days);
    customs clearance in Vladivostok (3 business days);
    transhipment to a low-bed trailer;
    road transport by low-bed trailer from Vladivostok to Yekaterinburg (10 days);
    development of a custom cargo securing system on the platform.
    Result: the cargo was delivered in 27 days without damage. The client received a full package of accompanying documents, including certificates of conformity.
  • Urgent delivery of a drilling rig from Shanghai to Tyumen
    Task: Transport an oversized drilling rig (length: 12 m, width: 3 m, height: 4 m, weight: 25.6 tons) for an oil and gas company in Tyumen.
    Solution: Disassemble the rig into its main modules for safe transportation;
    Trucking from Shanghai to Manzhouli (4 days);
    Consolidation at our temporary storage warehouse (1 day);
    Trucking from Manzhouli to Tyumen (8 days);
    Oversized cargo transportation permits within the Russian Federation;
    Result: The rig was delivered in 13 days. All stages were monitored online by a logistics specialist. No damage was detected, and assembly was completed on time.
  • Transporting a production line from Guangzhou to Voronezh
    Task: Transport a production line (length: 18 m, width: 3 m, height: 3 m, total weight: 46 t) from Guangzhou to a plant in the Voronezh region.
    Solution: Trucking from Guangzhou to Manzhouli (3 days);
    Consolidation at our temporary storage warehouse (1 day);
    Oversized cargo transportation permits within the Russian Federation;
    Trucking on a telescopic trailer from Manzhouli to Voronezh (13 days).
    Result: The production line was delivered in 17 days. The client received a full set of accompanying documents.
  • Delivery of 8 aerial platforms from Yiwu to Krasnoyarsk
    Task: Deliver 8 oversized aerial work platforms (total weight ~120 t) from Yiwu to a construction site in Krasnoyarsk by road.
    Solution: 4 lowboys, each carrying 2 aerial work platforms.
    Preparation (5 days): Measurements, route approval, special permits (China and Russia), insurance.
    Loading (3 days): Loading by crane (≥50 t), securing to a platform.
    Transportation (8 days): Column/sequential movement, GPS tracking.
    Unloading (2 days): Unloading by crane, condition inspection, signing of documents.
    Final delivery time: 19 days
    Cargo insurance for the entire route.
    Result: The equipment arrived in 19 days. All units are ready for use.